First phase of Reed Market Road nearly done

By KTVZ.COM news sources
Published On: Aug 28 2013 06:49:24 PM CDT
Updated On: Aug 28 2013 06:55:11 PM CDT
Reed Market Road project map

City of Bend

Widening project for Reed Market Road in southeast Bend includes center turn lane, bike lanes and sidewalks

BEND, Ore. -

The first stage of the Reed Market project will be complete and open to traffic Friday, Sept.  6, city official said.  Reed Market will be open from Newberry Drive (the Senior Center) to Teakwood Drive.  Admiral Way and Teakwood Drive will be open to local traffic.

The second stage of the Reed Market project will begin Friday, September 6.  Reed Market will be closed from Shadowood Drive to west of Orion Drive, Orion Drive will remain open.  The closure is required to continue the re-construction of Reed Market Road.  The work is being be performed by local contractor Jack Robinson & Sons.

A temporary, signed detour route for Reed Market through traffic will be in effect for the duration of construction. Traffic will continue to utilize SE15th Street, NE Bear Creek Road, SE 27th Street and SE Ferguson Road.

Email questions or comments to streetbond@ci.bend.or.us, or call the project hotline at 541-388-5547.

For more information, visit www.bendoregon.gov/GOBond.